EPC Al-Zaferaniyah Gravity Trunk line Sewer-Baghdad

Client: Parsons/ Bechtel Int. /USAID. (Oct 2004)
Location: Baghdad
Planned Duration: 18 Months
Actual Duration: 16 Months

Work included installation of 5km of trunk line sewer, GRP Pipe of sizes from 900mm – 2100mm – starting depth is 4M depth, final depth is 11.5m (Gravity Line) – 40 large collector manholes.

Kufan employed state-of-art techniques in trench shoring, and dewatering techniques.