Camp Halfaya

Client: Baker Hughes
Location: Halfaya Oil Field (Missan Oil Company)
Planned Duration: 180 days (Critical Schedule delivery)
Actual Duration: 180 Days

A fast track project (work was around the clock on three shifts) to accommodate 65 people in 180 days. Work included design, supply, construction & Facility Management to include the following :

  • Construction of 3 Accommodation Quarters (single & double bed  rooms)
  • Office Complex Hall, Recreation Area, Clinic, Large Kitchen & Dining Facility
  • Workshop, Storage Yard, Parking Lot and Entry Control
  • Power Generation (total 3 Generator Sets of various power rates)
  • Water Treatment Facility & Distribution Network